Question: 1 / 105

What are three critical inputs to the Solution post-PI Planning?

Program PI Objectives from all ARTs

The selection of Program PI Objectives from all Agile Release Trains (ARTs) as a critical input to the Solution post-PI Planning is vital because these objectives define the goals and outcomes that the teams within the ARTs aim to achieve during the upcoming Program Increment (PI). By compiling these objectives, stakeholders can ensure alignment across various teams and enhance transparency regarding what each ART is focused on delivering. This alignment is crucial for integrating efforts and achieving broader organizational goals, particularly in a scaled agile environment where coordination among multiple teams is essential.

Program PI Objectives serve as a common reference point that helps teams manage their work in relation to one another and allows for better planning and decision-making in the post-PI context. They also facilitate tracking progress and assessing the overall success of the PI, making them a necessary component of effective solution delivery and strategy execution.

In contrast, while the solution planning board, model-based systems engineering diagrams, and system teams' interfaces are important artifacts and concepts in the context of solution development, they do not serve as the primary focus for input into the Solution post-PI Planning in the same way that Program PI Objectives do. Their roles, while significant, surround facilitating clarity and integration rather than directly outlining the explicit goals for the upcoming increment.

Solution planning board

Model-Based Systems Engineering diagrams

System Teams' interfaces